Grati I - Delivery of steam turbine turning gear synchronization module

Object description: Delivery of steam turbine turning gear synchronization module

Used products: TGS Z 110

Branches: Automation for Conventional Power Generation, Thermal power plants

Country: Indonesia

Realisation: 5/2018

Finished at: 2018

Text

Direct customer - Doosan Škoda Power s.r.o.,

Main supplier - Ansaldo Energia + Lotte Engineering & Construction

Final customer/ Investor – PT PLN company Indonesia Power

Scope of ZAT delivery – delivery of steam turbine turning gear synchronization modul, used system, SandRA TGS Z110;

Points of Interest:

Steam turbine supplier - Doosan Škoda Power s.r.o.

Combined cycle 2GT+1ST, 2x air cooled generator, total power output 500MW

Delivery term of main parts – 9/2017

Expected term of commissioning – 5/2018 (PAC); 8/2019 (FAC)