We managed realization of the revitalization project of Týniště nad Orlicí - Broumov track in a record - breaking time

We managed realization of the revitalization project of Týniště nad Orlicí - Broumov track in a record - breaking time

At the end of last year the Transport group of Smart System Division faced the challenge to realize 1st phase of the Týniště nad Orlicí – Broumov track revitalization project. Regarding conditions on the site we had to manage the technology tests and set up of the application in 4 days instead of 10 day time. Our readiness and professional work was also appreciated by the SŽDC Electrotechnology and energy administration that described ZAT as the well prepared site supplier.

Subject of the 1st phase supply was represented by application software for control and monitoring of the replacement electric heat, lighting and electronic security system for premises administred by SŽDC. Our application assisted in safe traffic on the course during Christmas time and will be used in this way from now on.

Currently we are working on the final second phase when we add camera technology, passengers´ information system, radio, electrometers etc in the application.      

Function of integration concentrators is represented by 5 pieces of our control system SandRA.

Total amount of the contract is 10,1 mil. CZK and the contract will have been completed by June 2019.